Can You Sue a Contractor for Not Pulling Permits?

The short answer

Yes. In Arizona you can generally sue a contractor for not pulling required permits when the contract or the law made permits the contractor's job and the failure cost you money. The usual claims are breach of contract and defective work, with damages for permit fees, inspections, corrections and penalties.

Key points
  • The missing permit is not the claim by itself. The claim is the cost it causes you.
  • Who had to pull the permit depends on your contract and the local building code.
  • A code violation can qualify as a construction defect under Arizona's dwelling statutes.
  • You can also file a Registrar of Contractors complaint against a licensed contractor.

When can you sue a contractor for not getting permits?

You can sue when the contractor was responsible for the permit, did not get it, and you were harmed as a result. Courts award damages for losses, so the question is what the missing permit has cost or will cost you.

The most common legal theories are:

  • Breach of contract. Many contracts say the contractor will obtain all permits, or will perform the work in compliance with applicable codes. Failing to do so breaches that promise. See our page on contract disputes.
  • Defective work. Arizona law implies a promise that construction will be done in a workmanlike manner. Work that cannot pass inspection usually falls short of it.
  • Misrepresentation. If the contractor told you permits were pulled, or that none were needed, to get the job or get paid, that statement may support a fraud or consumer fraud claim. A.R.S. § 44-1522 prohibits deception and misrepresentation in connection with the sale of merchandise, a term the act defines to include services.

For a home, the statutes add support. A.R.S. § 12-1361 defines a construction defect to include a material deficiency that results from a violation of the construction codes adopted by the city, town or county where the dwelling is located.

Who is responsible for pulling permits, the owner or the contractor?

It depends on the contract and the local code, but in most contractor-run projects the contractor applies for the permit. Start with the contract language. Look for a permits clause, a code compliance clause, and the line items in the bid.

Be aware of two points that surprise owners. First, the city or county generally looks to the property owner to correct unpermitted work, whoever caused it. Second, if you signed an owner-builder permit application at the contractor's suggestion, you may have taken on responsibilities the contractor would otherwise carry. A contractor who asks you to pull the permit yourself is a warning sign worth checking against the license records at the Arizona Registrar of Contractors.

If the contract is silent, the answer turns on what was said, industry practice and the building code. Those are fact questions a lawyer can evaluate from your documents.

What damages can you recover for unpermitted work?

You can generally recover the reasonable cost of bringing the work into compliance, plus other losses the failure caused. The amounts vary widely by project, so get them documented in writing.

LossProof to gather
After-the-fact permit and plan review feesReceipts from the building department
Opening walls, ceilings or slabs for inspection, and restoring themWritten estimate or invoice from a licensed contractor
Correcting work that fails inspectionInspection report and repair bid
Penalties or stop-work costs charged by the city or countyNotices and payment records
A lost or delayed sale or refinanceContract, lender or escrow correspondence

If the work is sound and passes a later inspection, your damages may be limited to the fees and the cost of the inspection process. If it must be torn out, they can approach the cost of the job. In a contested contract case the court may also award the successful party reasonable attorney fees. Our post on recovering attorney fees in an Arizona contract case explains how that works.

What should you do when you find out there was no permit?

Confirm the facts in writing before you confront anyone or pay anything more. A calm paper trail is worth more than an angry phone call.

  1. Check the permit record. Search your address with the city or county building department, or call the permit counter, and save what you find.
  2. Reread the contract. Mark every clause on permits, code compliance, inspections and warranty.
  3. Ask the contractor in writing. Request the permit number and inspection sign-offs by email or letter.
  4. Get an independent assessment. Have a licensed contractor or design professional tell you what it will take to permit and pass the work.
  5. Hold your documents. Keep texts, invoices, photos taken during construction, and proof of payment.
  6. Send a written demand. Give the contractor a deadline to obtain the permit and correct the work at its own cost. A lawyer's demand letter sets up the claim if the contractor refuses.
  7. Give statutory notice if required. Construction defect claims on a dwelling generally require certified mail notice and an opportunity to repair before suit.

Do not ignore the problem and hope it goes unnoticed. Unpermitted work tends to surface during a sale, and a seller's disclosure duties do not disappear because a contractor cut the corner. See what a seller must disclose when selling a house in Arizona.

Can you report the contractor to the Registrar instead?

You can do both. A licensed contractor can be the subject of a written complaint to the Registrar of Contractors under A.R.S. § 32-1155, which the Registrar investigates and may follow with a citation. Building code problems fall within the kind of workmanship complaint that process is designed for.

The Registrar's process can produce an order to fix the work or discipline against the license. It does not replace a lawsuit for your full losses, and it has its own filing deadline. Our post on filing a complaint with the Arizona Registrar of Contractors explains the steps.

Your next step: pull the permit history for your address and put it beside your contract. If the contract gave the permit job to the contractor and the record is empty, you likely have a claim worth reviewing. Touma Law handles contractor disputes for Arizona owners and contractors. Request a free case evaluation and bring both documents.

This article relates to the firm's contractor disputes practice. If the situation it describes is yours, the facts and the deadline matter more than the general rule.

Request a free case evaluation →
Sources
  • A.R.S. § 44-1522 Unlawful practices; intended interpretation of provisions. Arizona Revised Statutes, Arizona Legislature.
  • A.R.S. § 12-1361 Definitions. Arizona Revised Statutes, Arizona Legislature.
  • A.R.S. § 32-1155 Filing of complaint; resolution of complaint; service of notice; failure to answer; prohibited citations. Arizona Revised Statutes, Arizona Legislature.
Attorney Simon Touma
Published by Touma Law, PLLC

Simon Touma is the founder of Touma Law, a Phoenix firm that represents businesses and individuals in contract, real estate and civil disputes across Arizona. Every statute cited in this article links to its text on the Arizona Legislature's website.

Updated November 2026. General information about Arizona law, not legal advice for your situation.

Questions

Common questions.

Q.Can I refuse to pay a contractor who did not pull permits?
A.

Withholding the full balance is risky. If the work has value and the contract requires payment, the contractor may sue or record a lien. A safer approach is to give written notice of the breach and withhold an amount tied to the documented cost of permitting and correcting the work. Get advice first.

Q.Do I have to disclose unpermitted work when I sell my house?
A.

Arizona sellers generally must disclose known facts that materially affect the value of the property, and known unpermitted work commonly falls in that category. Resolving the permit before listing is usually better than disclosing an open problem. A buyer who learns of it later may have claims against the seller.

Q.Can I get a permit after the work is finished?
A.

Often, yes. Many Arizona building departments will issue a permit for completed work, sometimes with added fees, but the inspector may require parts of the work to be exposed so it can be inspected. Ask your city or county building department what its process requires before any work is opened up.

Confidential case evaluation

Speak with counsel.

Attorney Simon ToumaCall us 24/7(602) 491-9223Simon Touma, Attorney

3101 N. Central Ave., Suite 610, Phoenix, AZ 85012

Request a free case evaluation

Tell us what happened. A member of the firm will contact you to discuss your case and next steps.

Submitting this form does not create an attorney-client relationship. Please do not send confidential information until one has been established.

Call (602) 491-9223Free evaluation