Anticipatory repudiation is a party's clear and unequivocal statement or act, made before its performance is due, showing that it will not perform the contract. The other party may generally treat the repudiation as a breach right away, stop its own performance and sue for damages, instead of waiting for the due date to pass.
- A repudiation must be clear and unequivocal. Doubts, complaints or requests to renegotiate are usually not enough.
- The non-breaching party can generally sue immediately without waiting for the performance date.
- A repudiation can often be retracted until the other side relies on it or says the contract is over.
- Treating an unclear statement as a repudiation is risky: if you stop performing, you may become the party in breach.
What counts as anticipatory repudiation?
Only a definite refusal counts. The repudiating party must show, by words or conduct, a positive and unequivocal intent not to perform when the time comes. Courts set the bar high because the consequence is serious: the other side gets to end the contract early and sue.
| Usually a repudiation | Usually not a repudiation |
|---|---|
| "We will not deliver the order." | "We are having trouble meeting the date." |
| "We are not paying unless you cut the price." (when the contract fixes the price) | "Can we talk about adjusting the price?" |
| Selling the promised property or goods to someone else | Listing the property while the contract is pending, without more |
| Shutting down the operation needed to perform | Rumors of financial trouble |
| Insisting on terms the contract does not contain as a condition of performing | A good faith disagreement about what the contract means |
Conduct can repudiate as clearly as words. A party who makes its own performance impossible, for example by transferring the subject of the contract to a third party, has repudiated even if it never says so. The gray area is the party who expresses reluctance or demands changes. Whether that crosses the line depends on the exact words used and the surrounding facts.
What can you do when the other party repudiates the contract?
You generally have a choice. Once the other side has clearly repudiated, you may treat the contract as breached now, or you may hold the contract open and give the other side a chance to change course.
- Treat it as a breach. You can stop your own performance, tell the other side the contract is terminated because of its repudiation, and sue for damages without waiting for the performance date.
- Wait and urge performance. You can keep the contract alive for a reasonable time and ask the other party to retract. The risk is that waiting too long can increase losses you will not be able to recover.
- Seek assurance. When the signals are worrying but not a clear refusal, you can demand written assurance that the other party will perform. In contracts for the sale of goods, Arizona's commercial code gives a party with reasonable grounds for insecurity the right to demand adequate assurance and to suspend its own performance until it receives it.
Whichever you choose, put it in writing. A letter that states what the other party said or did, why it amounts to a repudiation, and what you intend to do creates the record a court will look at later. Our demand letters page explains how that correspondence is used.
Can a party take back a repudiation?
Often yes, if it acts in time. A repudiating party can generally retract and restore the contract until the other party has materially changed its position in reliance on the repudiation, or has indicated that it considers the repudiation final, for example by terminating or filing suit.
This rule creates a practical race. If you want out of the contract after a repudiation, say so promptly and in writing, or take a clear step in reliance such as signing a replacement contract. If you would prefer performance, a written request to retract by a specific date makes your position clear and limits later argument about who ended the deal.
A retraction has to be real. The party must make clear that it will perform the contract as written, and it may need to provide any assurance that was justifiably demanded. A partial or conditional retraction can simply be a second repudiation.
What damages are available, and how long do you have to sue?
The damages are the same as for any breach: the amount that puts you where full performance would have, less what you saved or could reasonably have avoided. After a repudiation you are expected to take reasonable steps to limit your loss, such as finding a substitute buyer, supplier or tenant. You generally cannot keep spending on performance the other side has refused and then bill them for it.
Common recoverable items include the difference between the contract price and the cost of a replacement deal, lost profits that can be proved with reasonable certainty, and expenses caused by the breach. If the contract fixes the amount in advance, see what liquidated damages are. In real estate contracts, the buyer's remedy may include an order compelling the sale, covered in whether a seller can back out of a real estate contract in Arizona.
Do not let the deadline run while you wait. For contracts for the sale of goods, A.R.S. § 47-2725 requires suit within four years after the cause of action accrues and says a cause of action accrues when the breach occurs, regardless of the aggrieved party's lack of knowledge of the breach. Other contracts follow different periods. Because a repudiation may be treated as the breach, count from the repudiation date to be safe, not from the later performance date.
Steps to take after an anticipatory breach
Mistakes in the first days after a repudiation are hard to undo. Follow this order:
- Preserve the repudiation. Save the email, text, letter or voicemail. If it was said in person, send a message confirming what was said and ask for a correction if you have it wrong.
- Reread the contract for notice, cure and termination procedures. Some contracts require written notice and a cure period even after a refusal to perform.
- Decide whether the refusal is clear. If it is ambiguous, ask in writing for confirmation or assurance before you stop performing.
- Do not breach first. Keep performing your own obligations until you have a clear repudiation or legal advice that you may stop.
- State your election in writing: terminated for repudiation, or contract held open until a date.
- Mitigate and document. Seek a reasonable substitute and keep records of every quote, replacement contract and added cost.
- Calendar the limitations date from the day of the repudiation.
Touma Law represents plaintiffs and defendants in Arizona contract disputes, including parties accused of repudiating. Bring the contract, the communication you believe was a refusal to perform, and your replacement costs, and request a free case evaluation.
This article relates to the firm's contract disputes practice. If the situation it describes is yours, the facts and the deadline matter more than the general rule.
Request a free case evaluation →- A.R.S. § 47-2725 Statute of limitations in contracts for sale. Arizona Revised Statutes, Arizona Legislature.