Phoenix Business Litigation 3101 N. Central Ave., Suite 610, Phoenix, AZ 85012Schedule a Free Case Evaluation
Business Litigation Disputes Real Estate Property Civil Litigation Torts Attorney Simon Touma Blog Articles Contact Phoenix
Contract DisputesPartnership DisputesBreach of Fiduciary DutyFraud & Financial MisconductNon-Compete & Trade SecretsDemand LettersReal Estate DisputesQuiet Title & PartitionBoundary & Neighbor DisputesCommercial Lease DisputesContractor DisputesCivil LitigationDefamation
Free case evaluation →Call (602) 491-9223

How Do You File a Mechanics' Lien in Arizona?

The short answer

To file a mechanics' lien in Arizona, serve a preliminary twenty day notice within 20 days after first furnishing labor or materials, record a sworn notice and claim of lien with the county recorder within 120 days after completion, serve a copy on the owner, and sue to foreclose within six months.

Key points
  • Lien rights start with the preliminary twenty day notice, long before anyone knows there will be a payment problem.
  • The lien must be recorded within 120 days after completion, or 60 days after a notice of completion is recorded.
  • The recorded lien must be under oath and include six items the statute lists.
  • The lien lapses six months after recording unless you file suit and record a notice of pendency of action.

What are the steps to file a mechanics' lien in Arizona?

There are five steps, each with its own deadline. A lien is a creature of statute, so each step should be followed closely and on time.

  1. Confirm you have lien rights. You must hold any contractor's license the work required, and on an owner-occupied home you need a written contract directly with the owner-occupant. See who can file a mechanics' lien in Arizona.
  2. Serve the preliminary twenty day notice. Mail it within twenty days after you first furnish labor, services or materials to the jobsite.
  3. Record the notice and claim of lien. Record it with the county recorder within 120 days after completion, or within 60 days after a notice of completion is recorded.
  4. Serve the owner. Serve a copy on the owner within a reasonable time after recording, if the owner can be found in the county.
  5. Foreclose within six months. File a lawsuit to enforce the lien and record a notice of pendency of action, or the lien expires.

What is the preliminary twenty day notice and who gets it?

It is a written notice that tells the owner you are on the project and may claim a lien if you are not paid. A.R.S. § 33-992.01 makes it a necessary prerequisite to the validity of a lien for everyone except a person performing actual labor for wages.

Serve it on the owner or reputed owner, the original contractor, the construction lender if any, and the person you contracted with. The statute allows first class mail with a certificate of mailing, or registered or certified mail, and service is complete when the notice is deposited in the mail. The notice must contain:

  • A general description of what you are furnishing and an estimate of the total price.
  • Your name and address.
  • The name of the person who contracted for your work or materials.
  • A description of the jobsite sufficient to identify it.
  • The statutory notice to the property owner, in the form the statute sets out.

Three practical points. If you miss the twenty days, send the notice anyway: you can still lien for what you furnished within twenty days before the notice and afterward. If your price grows to exceed the estimate by thirty percent or more, send a new notice. And keep your proof of mailing, because a copy of the notice and that proof must be attached to the lien.

What must an Arizona notice and claim of lien include?

The lien must be made under oath by the claimant or someone with knowledge of the facts, and A.R.S. § 33-993 lists what it must contain.

Required itemWhere to get it
Legal description of the propertyThe recorded deed or a title company
Name of the owner or reputed owner, and of the person who hired youRecorder's records; your contract
The contract: a copy if written, or its terms, time given and conditions if oralYour project file
Your demand, after deducting just credits and offsetsYour invoices and payment ledger
Date of completionPermit records; your job log
Date the preliminary notice was given, with a copy and proof of mailing attachedYour mailing records

Record the lien in the county where the property is located. In the Phoenix area that is the Maricopa County Recorder. Use the legal description, not just the street address, and state the amount accurately. Overstating the demand invites a challenge and, in a bad case, a wrongful lien claim.

When does the 120 days to record a lien start?

It starts at "completion," which A.R.S. § 33-993 defines as the earliest of two events: thirty days after final inspection and written final acceptance by the governmental body that issued the building permit, or cessation of labor for sixty consecutive days (unless the stoppage is due to a strike, shortage of materials or act of God).

If no building permit was issued, or the permitting body does not issue final inspections and written acceptances, completion means the last date any labor, materials, fixtures or tools were furnished to the property.

Owners can shorten your time. If the owner records a notice of completion, the deadline becomes sixty days after that recording. The owner must mail you a copy within fifteen days of recording if you served a preliminary notice. If the owner fails to do that, you keep the full 120 days. On a residential project with several separate buildings, each building is treated as a separate work with its own clock.

What happens after the lien is recorded?

The lien gives you six months of leverage, and then it ends unless you sue. Under A.R.S. § 33-998, a lien does not continue longer than six months after it is recorded unless an action to enforce it is brought within that period and a notice of pendency of action is recorded. Under A.R.S. § 12-1191, a lien claimant must file that notice within five days of filing the action.

The foreclosure suit is usually combined with a breach of contract claim for the unpaid balance. The court may award the successful party reasonable attorney fees, so weigh the strength of the claim before filing. Our post on what a lis pendens is in Arizona explains the recorded notice.

If you are paid, record a release promptly. Leaving a satisfied lien of record exposes you to a claim by the owner.

Today, find three dates: your first day furnishing labor or materials, the date your preliminary notice was mailed, and the completion date. Touma Law represents contractors, suppliers and owners in contractor and lien disputes. Request a free case evaluation while there is still time on the 120-day and six-month clocks.

This article relates to the firm's contractor disputes practice. If the situation it describes is yours, the facts and the deadline matter more than the general rule.

Request a free case evaluation →
Sources
  • A.R.S. § 33-992.01 Preliminary twenty day notice; definitions; content; election; waiver; service; single service; contract. Arizona Revised Statutes, Arizona Legislature.
  • A.R.S. § 33-993 Procedure to perfect lien; notice and claim of lien; service; recording; definitions. Arizona Revised Statutes, Arizona Legislature.
  • A.R.S. § 33-998 Limitation of action to foreclose lien; attorney fees. Arizona Revised Statutes, Arizona Legislature.
  • A.R.S. § 12-1191 Notice of pendency of action affecting title to real property; filing; constructive notice to purchaser or encumbrancer; release of notice of pendency of action. Arizona Revised Statutes, Arizona Legislature.
Attorney Simon Touma
Published by Touma Law, PLLC

Simon Touma is the founder of Touma Law, a Phoenix firm that represents businesses and individuals in contract, real estate and civil disputes across Arizona. Every statute cited in this article links to its text on the Arizona Legislature's website.

Updated November 2026. General information about Arizona law, not legal advice for your situation.

Questions

Common questions.

Q.Can I file a mechanics' lien myself without a lawyer?
A.

An individual claimant can prepare and record a lien, and the recorder will accept a document that meets recording standards without judging its legal validity. The risk is that one error in the legal description, dates or attachments can void the lien. The foreclosure lawsuit that follows is where most claimants need counsel.

Q.Does it cost money to record a mechanics' lien?
A.

Yes. The county recorder charges a recording fee set by its fee schedule, and you will have mailing costs for the preliminary notice and service on the owner. Those costs are small compared with the filing and service costs of a foreclosure suit if the lien does not prompt payment.

Q.Can I lien for unpaid change orders or extra work?
A.

Generally yes, if the extra labor or materials actually went into the project and you can prove the owner or the owner's agent authorized them. Keep signed change orders. If extras push your price thirty percent or more above your preliminary notice estimate, the statute calls for an updated notice.

Confidential case evaluation

Speak with counsel.

Attorney Simon ToumaCall us 24/7(602) 491-9223Simon Touma, Attorney

3101 N. Central Ave., Suite 610, Phoenix, AZ 85012

Request a free case evaluation

Tell us what happened. A member of the firm will contact you to discuss your case and next steps.

Submitting this form does not create an attorney-client relationship. Please do not send confidential information until one has been established.

Call (602) 491-9223Free evaluation