A mechanics' lien is a claim recorded against real property by someone who supplied labor, professional services or materials to improve it and was not paid. In Arizona the lien secures the debt with the property itself, can cloud the title, and expires six months after recording unless a foreclosure lawsuit is filed.
- A mechanics' lien makes the property security for an unpaid construction bill.
- The claimant usually must serve a preliminary twenty day notice early in the job and record the lien within 120 days after completion.
- The lien lasts only six months after recording unless the claimant sues to foreclose it.
- Owner-occupied homes have special protection against liens from people the owner never contracted with.
How does a mechanics' lien work in Arizona?
The lien attaches the unpaid bill to the land and building, not just to the person who owes it. Under A.R.S. § 33-981, every person who labors or furnishes professional services, materials, machinery, fixtures or tools in the construction, alteration or repair of a building or other improvement has a lien on it for that work.
The same statute treats the contractor, subcontractor, architect or other person in charge of the work as the owner's agent for lien purposes. That is why an owner who paid the general contractor in full can still receive a lien from an unpaid subcontractor or supplier the owner never met.
The name is historical. "Mechanic" is an old word for a tradesperson, and Arizona statutes also call these mechanics' and materialmen's liens. They have nothing to do with auto repair shops.
What does a mechanics' lien do to your property?
A recorded lien clouds the title. It appears in the county recorder's records, where any buyer, lender or title company will find it.
- Sale and refinance. Title insurers generally will not insure over an unresolved lien, so closings stall until it is paid, released or bonded around.
- Foreclosure. The claimant can sue to foreclose the lien and ask the court to order the property sold to pay the debt.
- Fees. In an action to enforce a lien, the court may award the successful party reasonable attorney fees under A.R.S. § 33-998. That applies to whichever side wins.
A lien is not a judgment. Recording one does not prove the money is owed. It preserves the claimant's position while the dispute is resolved. If the lien is tied up with other title problems, see our page on quiet title actions.
What are the deadlines for an Arizona mechanics' lien?
Arizona lien rights are created and lost by the calendar. Each step below has a statutory deadline, and missing one generally defeats the lien.
| Step | Deadline | Statute |
|---|---|---|
| Serve preliminary twenty day notice | Within 20 days after first furnishing labor or materials | A.R.S. § 33-992.01 |
| Record notice and claim of lien | Within 120 days after completion, or 60 days after a notice of completion is recorded | A.R.S. § 33-993 |
| Sue to foreclose and record a notice of pendency of action | Within six months after the lien is recorded | A.R.S. § 33-998 |
"Completion" has a specific meaning in A.R.S. § 33-993. It is the earlier of thirty days after final inspection and written final acceptance by the body that issued the building permit, or sixty consecutive days with no labor on the job (other than a stoppage caused by a strike, material shortage or act of God). Where no permit was issued, completion is the last date labor, materials, fixtures or tools were furnished.
The foreclosure suit comes with a recorded notice of pendency of action, often called a lis pendens. Our post on what a lis pendens is in Arizona explains that document.
Can a mechanics' lien be recorded against your home?
Sometimes, but Arizona gives owner-occupants strong protection. Under A.R.S. § 33-1002, no mechanics' lien is allowed against the dwelling of an owner-occupant except by a person who signed a written contract directly with that owner-occupant.
In practice this means a subcontractor or supplier hired by your general contractor usually cannot lien the house you live in. The protection has conditions:
- The property must be a dwelling designed for single one-family or two-family residential use, which includes a condominium.
- The owner must be a natural person who held recorded title before the work began.
- The owner must live in the home, or intend to live in it, for at least thirty days in the twelve months after completion, and must not intend to sell or lease it.
The statute also says any agreement that waives this protection is void. It does not protect rental houses, homes built to sell, or commercial property, and title held in a business entity raises questions a lawyer should review.
What should you do if a lien or lien notice shows up?
First, identify the document. A preliminary twenty day notice is not a lien. The statutory form says so in its first line. It is a warning that someone on your project is preserving lien rights, and it is your cue to collect lien waivers before you release payments.
If an actual notice and claim of lien has been recorded, note the recording date, because the six-month clock in A.R.S. § 33-998 starts there. Then compare the lien against the deadlines in the table above. Our posts on how to fight a mechanics' lien on your property and who can file a mechanics' lien walk through the defenses.
Gather the recorded lien, every preliminary notice you received, your contract, and proof of what you paid and to whom. Touma Law represents owners, contractors and suppliers in contractor and lien disputes. Request a free case evaluation and bring the recording date with you.
This article relates to the firm's contractor disputes practice. If the situation it describes is yours, the facts and the deadline matter more than the general rule.
Request a free case evaluation →- A.R.S. § 33-981 Lien for labor; professional services or materials used in construction, alteration or repair of structures; preliminary twenty day notice; exceptions. Arizona Revised Statutes, Arizona Legislature.
- A.R.S. § 33-998 Limitation of action to foreclose lien; attorney fees. Arizona Revised Statutes, Arizona Legislature.
- A.R.S. § 33-992.01 Preliminary twenty day notice; definitions; content; election; waiver; service; single service; contract. Arizona Revised Statutes, Arizona Legislature.
- A.R.S. § 33-993 Procedure to perfect lien; notice and claim of lien; service; recording; definitions. Arizona Revised Statutes, Arizona Legislature.
- A.R.S. § 33-1002 Definitions; inapplicability of certain liens to owner-occupied dwelling; waiver void. Arizona Revised Statutes, Arizona Legislature.